What is Progress billing?

Progress billing for contractors: how milestone payment schedules work, a worked install example, deposit limits like California's, and over-billing risks.

Updated October 15, 2026 · 6 min read

Definition

Progress billing is invoicing a large job in stages as the work moves forward, such as a deposit at signing, a payment at rough-in and the balance at completion, instead of one invoice at the end. It protects the contractor's cash flow on jobs with big equipment and labor costs, and many states limit how much can be collected before work is done.

Also called: progress payments, milestone billing, staged billing, draw schedule, progress invoicing

Used for
Installs, remodels, new construction, multi-day projects
Billed by
Milestone or percent complete
Agreed in
The signed estimate or contract
Legal limits
Set by state; e.g. California caps deposits at 10% or $1,000
Watch for
Billing ahead of the work done

On a $15,000 heat pump and duct replacement, a contractor might spend $7,000 on equipment and pay a crew for three days before the job is finished. Billing it all at the end means carrying that cost for a week or more, and longer if the customer pays slowly. Progress billing spreads the invoice across the job so cash comes in closer to when it goes out.

Progress billing in plain English

Instead of one invoice at completion, the job is split into stages, each tied to something both sides can see: the contract signed, equipment delivered, rough-in inspected, system started up. When a stage is reached, you invoice that stage's amount. The schedule is agreed up front, in writing, so nobody is surprised.

There are two common ways to set the stages:

  • Milestone billing. Fixed amounts at named events. Simple and easy for homeowners to follow. Most residential trade work uses this.
  • Percent-complete billing. Each invoice covers the share of the job finished since the last one. Common on commercial and construction projects with a general contractor reviewing each pay application.

A worked example: a milestone schedule

Made-up numbers for a $15,000 residential heat pump and duct replacement in a state with a California-style deposit cap:

StageTriggerAmountRunning total billed
Down paymentContract signed$1,000$1,000
Equipment deliveredEquipment on site$6,000$7,000
Rough-in completeDuctwork and line set installed, inspection passed$4,500$11,500
FinalSystem started, commissioned, final inspection passed$3,500$15,000

The down payment is capped at $1,000 because 10% of $15,000 would be $1,500 and the California rule takes the lesser of the two.1 The equipment payment is triggered by delivery to the site rather than by ordering, which keeps payments from running ahead of the work. The final payment is large enough that the customer has a reason to see the job through inspection with you, and small enough that you aren't carrying most of the cost.

What do the rules say about deposits and progress payments?

Deposit and payment rules for home improvement work are set by states, and they vary. California is a widely cited example. Its Contractors State License Board tells consumers that "by law, a down payment cannot exceed 10 percent of the project price or $1,000, whichever is less," and advises them not to let payments get ahead of the work.1

10% or $1,000

California's cap on a home improvement down payment, whichever is less

CSLB

Progress billing and revenue

A progress invoice is a bill, not necessarily revenue. For accrual-basis financial statements, revenue follows ASC 606, which recognizes revenue as promised goods or services are transferred to the customer.2 If you bill $7,000 when equipment is delivered but have done only $5,000 of work, the extra $2,000 is closer to deferred revenue than to income. Construction accountants call that gap over-billing; the opposite is under-billing.

 Over-billedUnder-billed
MeansInvoiced more than the work completedCompleted more work than invoiced
Cash effectCustomer is financing youYou are financing the customer
On the balance sheetA liability: work still owedAn asset: work not yet billed
RiskSpending cash you'll need to finish the jobRunning short of cash mid-project

Taxes have their own timing rules. IRS Publication 538 points contractors using long-term contract methods to section 460 of the Internal Revenue Code and its regulations,3 and the exceptions that apply to smaller contractors and home construction contracts are a conversation for your tax preparer.

Common progress billing mistakes

  • No schedule in the signed estimate. If the stages aren't in writing before work starts, every invoice becomes a negotiation.
  • Vague triggers. "Halfway" is an argument. "Rough-in inspection passed" is a fact.
  • Billing ahead of the work. It can breach state rules and leaves you owing work you've already been paid for.
  • Waiting to invoice. A stage reached on Tuesday and billed the following Monday adds six days to your receivables.
  • Folding change orders into stages. Price and sign each change order separately, then bill it clearly.
  • A tiny final payment. If 95% is collected before the last inspection, there's little reason for anyone to hurry back for punch-list items.

Before you send a progress-billed contract

  • Deposit amount checked against your state's rule
  • Each stage tied to an event you can document with a photo or inspection
  • Amounts that track cost: equipment payment no larger than equipment delivered
  • A meaningful final payment tied to commissioning and final inspection
  • Change order process and pricing described
  • How each stage will be paid: card, bank transfer or check

Collecting each stage

Payment method matters on large stages. Stripe's published US pricing is 2.9% + 30¢ for online card payments and 0.8% capped at $5 for ACH bank debits.4 On a $6,000 equipment payment, that's about $174.30 by card online versus $5 by bank debit, worked from the published rates. Bank debits take longer to confirm, so ask for them early enough that the payment clears before you need the cash.

Progress billing in TradesWork

Be clear on this one: TradesWork doesn't do progress billing today. The job costing feature lists no project budget, WIP schedule or progress billing for construction-style jobs among its limits, and payments take no deposits on proposals or invoices yet. If most of your revenue is staged construction work, that's a real gap to weigh.

What TradesWork does cover around large jobs: estimated vs actual job costing on installs sold from an estimate, so you can see where a job ran over, and payment by card, Tap to Pay on a supported phone or bank account through a Stripe account your company owns, with bank payments shown as processing until they clear.

Footnotes

  1. Contractors State License Board (California), "What You Should Know Before You Hire a Contractor," sections on illegally large down payments and payments. https://www.cslb.ca.gov/seniors ↩ ↩2

  2. IFRS Foundation, IFRS 15 Revenue from Contracts with Customers (issued in May 2014 together with Topic 606 in the FASB Accounting Standards Codification). https://www.ifrs.org/issued-standards/list-of-standards/ifrs-15-revenue-from-contracts-with-customers/ ↩

  3. Internal Revenue Service, Publication 538, Accounting Periods and Methods. https://www.irs.gov/publications/p538 ↩

  4. Stripe, "Pricing," standard US rates, checked October 2026. https://stripe.com/pricing ↩

Free download

Home Service Business Plan Template

A fill-in-the-blanks business plan for HVAC, plumbing, electrical and other home service companies.

Get it free
  • Fill-in business plan in Word
  • Services, pricing and market sections with prompts
  • Marketing and staffing plan
  • Startup costs and 3-year financial outline
  • Works for any trade

Frequently asked questions

A deposit is a single payment before work starts, usually to order equipment and hold a date. Progress billing is the whole schedule: the deposit, payments at agreed milestones and the final balance. A deposit is often the first step of a progress billing schedule, but a job can have a deposit with no further stages, or stages with no deposit.

Ready to run a tighter shop?

Try TradesWork free for 14 days. Bring your customers and price book, or start fresh with a price book made for your trade.

  • No credit card
  • No contract
  • Cancel any time
Three workers in coveralls unloading equipment from a van